PDS 2021 South Bahrain Loop Road-Stage 2

Projects Description :

Project Name: SOUTH BAHRAIN LOOP ROADS (SBLR) STAGE 2 (PACKAGE A)

Client: Ministry of Works

Consultant: MOW, Roads Projects and Maintenance Directorate

Main Contractor: Nass Contracting Co. W.L.L

Contract Type: Lumpsum

Duration: 01st April 2020 to 31st March 2021

Location: Al Jazair, Kingdom of Bahrain

Work Description:
Link road in-between Gulf of Bahrain Road with Al Sahel Development. Approximately 10.0 km new road will be constructed as a dual two-lane carriageway with associated storm water drainage and other utility works (Package-A: 4,700m) The Scope of works consisting of the following:

  • 4700m Road Works (2 Lanes Dual Carriageway)
  • Road Marking and Signage Work
  • Drainage Works (Storm Water Line 3,760m)
  • TSE Line (5,000m)
  • Street Lighting and Miscellaneous Works
  • 8m Deep Pumping Station including MEP
  • 3 Nos. Culvert and 1 No. Outfall
  • Safety Barriers (Concrete and TCB)